Wednesday, May 2, 2012

Modified Short-Term Schedule:


RFQ Responders, please note that Submittals received on April 27th are currently being reviewed by CDPHE,  the Board of Trustees, the ARWRF Board and Landowners.  There are 7 or 8 reviewers, so this may take 2 weeks to complete.  Any necessary follow-up interviews and/or Site Visits will be scheduled on approximately May 17th for sometime during the 2-4 weeks after that.  Interviews and Site Visits may or may not be needed, at the discretion of the review group. 


Please note that the final decision on Designer may be sometime in late June, rather than the end of May as listed in the Draft Schedule.